Days

perimeter walls of brick


Today I have not too much to report, because it has not optically changed all too much in construction.

The canopy is "tight" and with a really red foil.





The brick work started again today in full swing and the ground floor is almost done.
All four walls are now completely bricked.




It looks great, in reality it has of course much better than the photos but it is always worth a picture.

What I like most are the final pieces of the windows and doors, and the closure rim the upper floor. Here
were on edge the stones and laid with the narrow side forward.

gemauert.Nun Upstairs were the outer walls of the nursery, bedroom and bathroom where once you see will be the ground level windows.




We have all the windows except the front door of the house all widened from 80 cm to 100 cm to more light in the house to have. There is nothing worse than not enough daylight in the rooms have to.

was then still a lot of insulation for the roof and the upper floor provided.

How can you see to fill a house with goods.



Then I am taking the time and studied our plan a bit.
Very interesting, because here you can see why such a stone can be built on stone house so fast. It's all thought out and top the logistics with the respective time window.

Here's a little insight into what the next 3 weeks, everything is coming our way.

week 41
Mon-Fri Masonry
Wed installation of windows, and I think the front door,
therefore we have already got the key

week 42
Mon Gable & Traufgesimse work
Tue / Wed outdoor painting
Thurs Plumbing
from Fr roofing

CW 43
from Mo drywall work
Mon roofing
from Thurs Carcass electrical installation shell installation
& Plumbing / Heating

The next insight for the next few weeks, the 10 weeks to get the keys then so 3 weeks.

Gee whiz, that's kind of a quick, first come grab me the box!?

So today rather less from the building, but more from the end.

a wonderful evening
your Inga